A. Applications for Macrocells Proposed under Chapter 16.66 LMC. In addition to the information requested in the conditional use application the following items shall be required for a WCF application:

1. A diagram or map showing the viewshed of the proposed facility.

2. Scaled site and elevation drawings and photosimulations of the proposed facility from affected residential properties and public rights-of-way at varying distances.

3. A site/landscaping plan showing the specific placement of the WCF on the site; showing the location of existing structures, trees, and other significant site features; and indicating type and locations of plant materials used to screen WCF components and the proposed color(s) for the WCF.

4. A signed statement indicating:

a. The applicant agrees to allow for the potential co-location of additional WCF requirement by other providers on the applicant’s structure or within the same site location; and

b. That the applicant agrees to remove the facility within eighteen months after that site’s use is discontinued.

5. A lease agreement with the landholder or letter of authorization from the owner allowing the provider to act as an agent for the landowner in a land use application.

6. Evaluation of reasonable camouflage or concealment technology that could be proposed to lessen the visual land use impacts from the facility.

7. Justification must be provided that the structure is necessary and essential, that other methods are not possible, such as use of existing structures (other towers, buildings, etc.) or use of other technological methods such as microcell technology where systems are built as part of cable systems and no towers are needed.

B. Applications submitted under Chapter 16.84 LMC may require additional information the administrator deems necessary to properly evaluate the application.

C. Applications proposed for small cells shall submit, in addition to a site plan review supplemental form:

1. Scaled site and elevation drawings and photosimulations of the proposed facility from affected properties and public rights-of-way at varying distances showing colors, placements, and size of antenna and all associated components of the WCF including radios, power services, all cables, and mounts.

2. A site plan showing the specific placement of the WCF, showing the location of existing structures, trees, and other significant site features.

3. If colocating on any structure, a structural analysis.

4. A lease agreement with the landowner or letter of authorization from the owner allowing the provider to act as an agent for the landowner in a land use application, if siting a small cell on private property. (Ord. 1546 §11, 2019; Ord. 1208 §69, 2003; Ord. 1192 §181, 2002; Ord. 1052 §1, 1997).