A. A permit shall become null, void and non-renewable if the permitted facility is not constructed and placed into use within eighteen months of the date of the city approval, provided that the permit may be extended one time for six months if construction has commenced before expiration of the original time period.

B. The permit shall expire and the applicant must remove the facility if the facility is not put into use within ninety days after construction or if use is discontinued for a period in excess of ninety days. If the facility is not so removed, the city may cause the facility to be removed and all expenses of removal shall be paid by the owner of the land where the facility is located.

C. The applicant shall maintain the WCF to standards that may be imposed by the city at the time of the granting of a permit. Such maintenance shall include, but shall not be limited to, maintenance of the paint, structural integrity and landscaping. If the applicant fails to maintain the facility, the city may undertake the maintenance at the expense of the applicant or terminate the permit, at the city’s sole option.

D. The applicant shall notify the city of all changes in ownership or operation of the facility within sixty days of the change. (Ord. 1546 §18, 2019; Ord. 1052 §1, 1997).